Great things are happening at the new school site.
- The admin/arts dome is completed and the other trades are beginning work inside.
- The Gym dome is inflated and insulated. South Industries
is currently building the dome structure inside. - The Cafetorium roof and stem walls are ready for insulation.
- The Middle School Dome has its stem wall forms in place and we will soon see the stem walls complete.
- The foundations are in and construction has begun on the wrestling room and soon the south connection building being built.
- We also will begin to see the exterior colors come to life.
Site Work
- Before winter we plan on having quite a bit of the site concrete in place as well as the entrance and re-work
of Hwy B well underway. - Before long we will see the internal road work, drives and parking lots taking form
Athletic Fields
- The fundraising for the athletic fields has started. Information about donation
opportunities including naming rights can be found on our website at: http://jconeteamonedream.com - This Spring we recognized the Glover Family the sponsor of the Football Field (Glover Family Field) after their $500,000 pledge. We have received a $100,000 pledge for the naming rights
of the baseball field as well as a $15,000 pledge from United Cooperative and a $10,000 from Avon Highlife. Watch for additional announcements. - Cash, donations can be sent to the District Office and are being kept in a designated fund.
- Pledge forms and naming rights’ contracts are available by contacting the District office at 920-699-2811.
Commitment
As stated before, the new facility is a long term asset for the community and your School Board and
No comments: